Low Boiler and High Boiler Lifting
Tandem lift using 2 mobile cranes (500 ton and 200 ton) of High Boiler and Low Boiler into position
High Boiler is a 45ton single piece equipment
A critical project milestone as lift involves
- Limitation of available Space for Crane setup
- Lift path involves crossing over operational critical facilities and live lines
- Effective planning and coordination required for the lift